Brush Street
Mix of Affordable & Attainable Housing
- Type
Volumetric Steel Modular Construction
- Location
Oakland, CA
- Status/Year
Pre-construction, May 2022
This project is targeted for 95 units consisting of affordable and attainable middle market housing. This is a HUD backed project. Synergy is contracted for full pre-construction services to take this project from inception to permit. We have completed a project feasibility package including a detailed pre-construction schedule, a comprehensive scope delineation exercise between Synergy and the modular manufacturer and a full ROM estimate. Additionally, we have completed the DD estimate and anticipate CD submittal in 4 months. We anticipate HUD financing to be in place and a construction start in April 2021.